FIRE STATION 93 DESIGN AND CONSTRUCT

FIRE STATION 93 DESIGN AND CONSTRUCT


Existing Condition Fire Station 93

Description: The City identified the need for an additional fire station to serve the growing West Fayetteville area in the late 1990’s. Since then, the City has collected impact fees for this facility and secured a station site on Lester Road. In consideration of the anticipated growth in this area, fire department staff re-evaluated and identified an alternate site which will better accommodate the facility and provide improved coverage to the area. Upon completion, Station 93 will significantly improves response times to this area, bringing times well within established City performance goals of five minutes or less. This station will also add capacity to the City’s overall existing fire protection.


Project Type: Public Safety – Fire


Proposed Project Year: 2018


Estimated Cost: $2,072,000


Budget Funding & Resources:

Design – $207,200

I FF/CPF – $150,000

Proposed SPLOST – $57,200

Construction – $1,864,800

FF/CPF – $922,000

Proposed SPLOST – $942,800


Current Status As of 0/0/0: A Request for Qualifications for a design/build team was developed and published on November 3, 2017. Ten design/build teams submitted Statements of Qualifications on December 4, 2017. The City’s team evaluated the SOQ’s and developed a short-list of four firms. These four firms will be interviewed by the City’s team on January 24, 2018. Goal is to award a contract by early February.