CITY OF FAYETTEVILLE BUILDING DEPARTMENT

PRELIMINARY
  • EROSION CONTROL
  • TEMPORARY POLE
FOUNDATION
  • FOOTING
  • IN GROUND ELECTRICAL
  • IN GROUND PLUMBING
  • SEWER (FROM BUILDING TO TAP)
SLAB
  • MAIN STRUCTURE
    (GRADE BEAMS)
  • SUBMIT FOUNDATION
    SURVEY
  • OBTAIN BUILDING PERMIT
    (ALL TRADE PERMITS REQUIRED)
ROUGHS
(FRAMING, ELECTRICAL,
MECHANICAL & PLUMBING)
  • ALL TRADES ROUGHED IN
  • SHEATHING NAIL PATTERN
INSULATION
  • REQUIRES APPROVAL OF
    ROUGH INSPECTIONS
UTILITY RELEASE
  • ELECTRICAL POWER AND
    GAS SERVICE RELEASED
FINALS
  • ALL TRADE FINALS
  • FINAL EROSION
CERTIFICATE
OF OCCUPANCY
  • ISSUED UPON APPROVAL
    OF ALL FINALS AND IMPACT
    FEE IS PAID (IF NOT PAID
    ALREADY)

REQUIRED INSPECTIONS / INSPECTION PROCEDURE